Draw the permanent support and the temporary support used to install it.

In this guide
PRACTICE PROMPT

Use this fictional setting to practise clear reasoning. It is not an assessment or institution paper.

The setting

A new opening formed in an existing masonry wall, 4 m wide.

Your task

Draw the permanent support and the temporary support used to install it.

What a useful response would show

Needling or propping shown, and the sequence implied by the drawing.

Reflect afterwards

  1. What assumption mattered most?
  2. What would you check before using this on a real project?